Welcome to the Netflix Partner Help Center. Have a question or need help with an issue? Send us a ticket and we'll help you to a resolution.

Backlot Estimated Delivery Date

Context

It is now possible to provide "Estimated Delivery Dates" through Backlot. This provides all stakeholders visibility into the scheduling of work.  The "Estimated Delivery Date" is used by Fulfillment Partners to notify project stakeholders of delivery delays. This has no bearing on the actual Due Date itself, which is rigid and determined by contractual considerations. 

Process

The data is exposed in the "Estimated Delivery Date" column in your dashboard*:

By default, the "Estimated Delivery Date" will be set to match the "Due Date", but can be edited by Fulfillment Partners once the processing of material has been scheduled. 

To edit the data simply select the Source Requests you wish to update using the tick boxes. Once selected the "Bulk Action" menu will appear at the bottom of the screen. Select the "Edit Estimated Delivery" button:

A fly-out panel will appear on the right-hand side of the UI:

EDD_Full.png

Here you have the opportunity to edit all source requests in bulk using the Date/Time boxes at the top and clicking "Apply to all" (highlighted in red). Alternatively, you can go through and give each Source Request a unique "Estimated Delivery Date" using the Date/Time boxes (highlighted in yellow).

In addition, you will need to select a reason for the adjusted due date from the drop-down menu. 

EDD_Zoom.png

 

Definitions and potential use-cases for each of these reasons can be found in the table below: 

Reason: Definition:  Example(s): 
Production schedule pushed  Any pushes in the schedule which the FP does not have control over.  The show did not start shooting the first episode until 3-weeks after the originally anticipated date due to unforeseen issues. 
QC delay If pre-QC results are not provided in time for the creation of deliverables. Pending pre-QC results for the VDM delays IMF creation/delivery; pre-QC results for M&E audio delays secondary audio creation/delivery, etc. 
Received workable materials late The prerequisite source material(s) which are needed to create & deliver the target asset in Backlot is not available.  Including, but not limited to: Netflix final proxies, audio M&E, audio printmaster, dialogue list/dubbing script, color-corrected master, etc. 
Fulfillment Partner delays The due date has been jeopardized for reasons not listed above. All prerequisite source materials were received when originally scheduled and delivery delays were attributed to mismanagement of internal resources. 

1. The VDM and final mix were provided on-time, but the IMF was not successfully delivered due to mistakes which were flagged in IaaS (Inspection as a Service).

2. Printmaster + M&E, final proxies, and dub scripts/dialogue lists were provided to a facility managing dubbing, but the mix was not QC'd and delivered in time due to scheduling issues during recording, etc. 

Early Delivery When working with branded content, vendors are required to update the Estimated Delivery Due Date when source requests are expected to deliver earlier than the due dates provided in Backlot. There are many downstream dependencies when a vendor delivers an asset (e.g. QC), and this information provides Netflix with the ability to be more flexible and proactive with the allocation of our resources. 

1. You received foreign dialogue tracks from a dubbing facility earlier than expected, enabling you to mix, QC and deliver earlier than the due date provided in Backlot. 

2. The episode/feature finished online editorial earlier than expected, pre-QC was completed (if applicable), and you now have access to the VDM and final mixes -- enabling you to create your IMF and deliver earlier than the due date provided in Backlot. 

Redelivery Requested by Netflix N/A

This reason code should be used whenever an Estimated Delivery Due Date is updated due to a Redelivery Request being issued.

 


Once you have entered your desired dates either in bulk or individually, click "Save".

Whenever updating "Estimated Delivery Dates" in Backlot, be sure to leave a comment to notify your Netflix Representative.

* Please note that if you are unable to see this column you may need to enable it within the "Customize Column" drop-down menu. 

 



Change Log:

2018-01-23

Revised Process- Provided a new entry for Estimated Delivery Date reason codes ("Redelivery Requested by Netflix").    

2018-01-12

Revised Process- Provided definitions and examples for each of the Estimated Delivery Date reason codes.

2017-07-17

Revised Process- Added new UI images and description to reflect the Reason Code drop-down menu.

2017-05-11

Revised Context  – Updated verbiage to clearly distinguish between "Estimated Delivery Dates" and "Due Dates". 
Revised Process  – All changes to "Estimated Delivery Dates" in Backlot should be accompanied by a Backlot comment. 

Was this article helpful?
2 out of 2 found this helpful